Three Chemical Projects under Construction in Shanxi Province in 2020

1. Fine chemical industry and new material circulation project of Shanxi Yaxin New Energy Technology Co., Ltd

The fine chemical industry and new material circulation project of Shanxi Yaxin Xinneng science and Technology Co., Ltd. is to produce 300000 t / a methanol and 68000 T / a synthetic ammonia from coke oven gas, which is located in Qingxu County Fine Chemical Industry Park of Taiyuan City, Shanxi Province. In the later stage, new material projects such as dmmn will be constructed to extend the downstream industrial chain of coke oven gas utilization.

The project uses coke oven gas from upstream coking by-product to produce methanol and synthetic ammonia, which is the key link between fine chemical industry and new material circulation project of Shanxi Yaxin New Energy Technology Co., Ltd., and will provide raw materials for the development of fine chemicals downstream.The total contract amount of the project is 806 million yuan, the contract period is 16 months, and the project covers an area of 200 acre. After the completion of the project, the annual after tax profit is about 102 million yuan.

2. Tongzhou 2.15 million tons / year coking project phase I project

Tongzhou Group Co., Ltd. annual output of 2.15 million tons of 6.25 meters tamping coke oven project is one of the key projects of Qinyuan County deepening transformation project construction year in 2019, with a total investment of 3.65 billion yuan, including coke oven main device, supporting construction coal preparation system, dry quenching device, chemical recovery device, environmental protection facilities, etc.

The first phase project mainly constructs 2 × 56 hole carbonization chamber with height of 6.25 m and 1.15 MT / a tamping coke oven; the second phase project mainly constructs 2 × 50 hole carbonization chamber with height of 6.25 m and 1 million ton stamp charging coke oven; at the same time, supporting construction of dry quenching device, coal preparation system, coke dry quenching system, chemical product recovery equipment, environmental protection facilities and public and auxiliary facilities, and 2 × 2.4 million tons coal washing project and 2 × 15 MW dry quenching surplusHeat recovery unit, 100000 t / a coke oven gas to LNG and 100000 t / a synthetic ammonia project.

3. Shanxi Jinyan Energy Technology Co., Ltd. phase II 2.53

million tons / year 7.1 meter top loading coking project

The project uses its own and paid replacement capacity to build a 2.53 million T / a 7.1 m top loading coking project. The main project is to build 2.53 million tons / year carbonization chamber height of 7.1 meters, 4 × 56 holes ht50-710 type three-stage reheating top charging coke oven, supporting the construction of 2 × 160t / h dry coke quenching device, installed capacity of 2 × 25MW CDQ waste heat power generation device, gas purification, chemical product recovery and other facilities. The project is in strict accordance with the latest national industrial policies and energy saving requirements, and reaches the special emission limit standard for environmental protection. Coke oven gas is used in ethylene glycol co production LNG project.

In August 2019, Shanxi Jinyan energy science and Technology Co., Ltd. officially started to lay the foundation for 5 million tons / year coking phase II. The project will build 2.5 million tons / year coking equipment, 2 × 15MW CDQ waste heat power generation, 600000 tons / year ethylene glycol and 300000 tons / year LNG unit.

Jinyan 5 million tons coking circular economic Park project is divided into two phases. At present, the first phase has been basically completed. The second phase of the project mainly includes 2.53 million tons of top loading coking project, the use of three-stage heating 7.1 m reheating top charging coke oven, supporting the construction of dry quenching device, CDQ waste heat power generation device, gas purification, chemical product recovery and other facilities, as well as an annual output of 600000 tons of B 2Chemical production projects such as methanol co production 300000 tons LNG project that have realized the effective grafting of high-tech and traditional industries.

Source: Sinopec News

Legal statement:

1. The information reprinted or sorted out by the global website of Epec.com comes from official public channels or indicated sources. We are committed to providing reasonable, accurate and complete information, but do not guarantee the reasonableness, accuracy and completeness of the information. We are not responsible for any loss or damage caused by unreasonable, inaccurate or omitted information.

2. Epec.com fully respects the intellectual property rights of original authors. We solemnly remind visitors: when reprinting or using the information on this website, please obey relevant laws and regulations of the People's Republic of China. This website does not take any responsibility in case of related intellectual property disputes or other disputes. At the same time, this website has independent intellectual property rights for the original information and website logo. If the intellectual property rights of this website are infringed , this website has the right to pursue legal responsibility.

3. The information services published on this website are only for the purpose of information reference, learning or communication, and do not represent the views of this website, nor constitute any sales suggestions.

4. If this website inadvertently infringes the intellectual property rights of others, please write or call to inform, and this website will adjust or delete immediately.

If you have questions or need further assistance, please email: global.epec@sinopec.com.

2020年山西省3个拟在建化工项目

1山西亚鑫新能科技有限公司精细化工及新材料循环项目

山西亚鑫新能科技有限公司精细化工及新材料循环项目焦炉气制30万吨/年甲醇联产合成氨,建设地在山西省太原市清徐县精细化工园内,主要建设30万吨/年甲醇、6.8万吨/年合成氨,后期甲醇将配套建设DMMn等新材料项目,使焦炉气利用下游产业链得以延伸。

该项目利用上游焦化副产的焦炉气生产甲醇联产合成氨,是山西亚鑫新能科技有限公司精细化工及新材料循环项目承上启下的关键,将为下游发展精细化学品提供原料来源。项目总包合同额8.06亿元,合同工期为16个月,项目占地面积约200亩,项目建成后,年税后利润约1.02亿元。

2、山西通洲215万吨/年焦化项目一期工程

通洲集团股份有限公司年产215万吨6.25米捣固焦炉项目是沁源县2019年深化转型项目建设年重点工程之一,总投资36.5亿元,包括焦炉主体装置、配套建设备煤系统、干法熄焦装置、化产回收装置、环保设施等

一期工程主要建设2×56孔炭化室高6.25115万吨/年捣固焦炉,二期工程主要建设2×50孔炭化室高6.25100万吨捣固焦炉,同时配套建设干熄焦装置,同步建设备煤系统、干法熄焦系统、化产回收装置、环保设施及公辅设施,配套建设2×240万吨洗煤项目、2×15MW干熄焦余热回收装置、10万吨/年焦炉煤气制LNG联产10万吨/年合成氨项目。

3、山西金岩能源科技有限公司二期253万吨/7.1米顶装焦化项目

该项目利用自有和有偿置换的产能,“上大关小”,建设二期253万吨/7.1米顶装焦化项目。主要建设253万吨/年炭化室高度7.14×56HT50-710型复热式三段加热顶装焦炉,配套建设2×160t/h干法熄焦装置、装机容量2×25MW干熄焦余热发电装置、煤气净化、化产回收等其他设施。项目严格按照国家最新产业政策,节能要求,达到环保特别排放限值标准。焦炉煤气用于乙二醇联产LNG项目。

20198月,山西金岩能源科技有限公司500万吨/年焦化二期正式开工奠基。该项目将建设250万吨/年焦化配套2×15MW干熄焦余热发电、60万吨/年乙二醇联产30万吨/LNG装置等。

金岩500万吨焦化循环经济园区项目分两期建设,目前一期已基本完成建设,项目二期建设内容主要包括253万吨顶装焦化项目,采用三段加热7.1米复热式顶装焦炉,配套建设干法熄焦装置、干熄焦余热发电装置、煤气净化、化产回收等其他设施,以及年产60万吨乙二醇联产30万吨LNG项目等化产项目,实现了高新技术与传统产业的有效嫁接。

来源:石化新闻

法律声明:

一、易派客国际站转载或整理发布的资讯信息均来自官方公开渠道或已注明来源,我们致力于提供合理、准确、完整的资讯信息,但不保证信息的合理性、准确性和完整性,且不对因信息的不合理、不准确或遗漏导致的任何损失或损害承担责任。

二、易派客国际站充分尊重原创作者的知识产权。我们郑重提醒访问者:在转载或使用本网站资讯信息时,请遵守中华人民共和国相关法律法规,若发生相关知识产权纠纷或其他纠纷,本网站不承担任何责任。同时,对本网站原创信息以及本网站标识,本网站享有自主知识产权。侵犯本网站之知识产权的,本网站有权追究其法律责任。

三、本网站发布的资讯服务,仅为提供更多信息以参考使用或者学习交流,并不代表本网站观点,也不构成任何销售建议。

四、若本网站无意中侵犯了他人知识产权,请来信或来电告之,本网站将立即调整或删除。

如有疑问或需要进一步帮助,请发送邮件至:global.epec@sinopec.com