Epec Global Information Service- Project Information-No. 5, 2020(中文版请见底部)


Tongwei Group released the "Development Plan for High-Purity Crystalline Silicon and Solar Cell Business 2020-2023", proposing that by 2023, the cumulative production capacity of high-purity crystalline silicon will reach 22-29 thousand tons, and the cumulative solar cell capacity will reach 80-100GW.

Invest in 30GW solar cell project

This 30GW high-efficiency solar cell and supporting project was jointly completed by Tongwei Co., Ltd. and its subsidiary Tongwei Solar, Chengdu Municipal People's Government, and Jintang County People's Government. The project covers an area of about 2500 acres. It is planned to focus on the unmanned high-efficiency battery intelligent manufacturing route, building intelligent factories, digital workshops, logistics and storage and related supporting facilities, and creating a global "green energy town".

It is reported that the estimated total investment of the project is about 20 billion yuan. Among them, the Chengdu Municipal People's Government and the Jintang County People's Government provide financial support of about 6 billion yuan according to the actual investment progress of the project through its subordinate state-owned investment companies, accounting for 30% of the total project investment; the company will reasonably determine the source of funds and payment methods in the future to ensure that the project will be successfully implemented.

Qijintang County People's Government will assist the company to strive for higher-level support policies and implement one-stop services in project establishment, environmental assessment, registration, construction planning, etc., to create a good environment of construction, production and operation.

The project will be implemented in four phases, of which the first and second phases are planned to invest 4 billion yuan each and construct 7.5GW each, for a total of 15GW high-efficiency solar cell projects. The third and fourth phases are planned to invest 6 billion yuan each and construct 7.5GW respectively, for a total of 15GW high-efficiency solar cell and supporting projects.

According to the plan, the first phase of the 7.5GW project will start before March 2020, and it will be completed and put into operation in 2021. The subsequent projects will be gradually completed and put into operation in the next 3-5 years according to market demand.

If using current market mainstream battery prices to calculate the project, it is estimated that after the project is completed and put into operation, it will increase its operating income by about 30 billion yuan / year, and the company's solar cell and supporting project capacity will reach 60GW. At the same time, with the implementation of new projects, technology choices based on large-size specifications, high-efficiency products such as Perc +, Topcon, and HJT will promote the continued reduction of non-silicon costs for solar cells.


Source: International Power Network


通威集团投建200亿元年产30GW太阳能电池项目


日前,通威集团发布《高纯晶硅和太阳能电池业务2020-2023年发展规划》,提出至2023年,高纯晶硅累计产能将达22-29万吨,太阳能电池累计产能将达80-100GW。

  投建30GW太阳能电池项目

  本次30GW高效太阳能电池及配套项目由通威股份及下属子公司通威太阳能、和成都市人民政府、金堂县人民政府共同参与完成。项目占地面积约2500亩,拟以高效电池无人智能制造路线为主,建设智能化工厂、数字化车间、物流仓储及相关配套设施,打造全球“绿色能源小镇”。

  据悉,项目预计总投资约200亿元。其中,成都市人民政府及金堂县人民政府通过下属国有投资公司按项目实际投资进度提供资金支持约60亿元,占项目总投资的30%;公司后续将合理确定资金来源、支付方式等,保证项目顺利实施。

  金堂县人民政府将协助公司争取上级扶持政策,并在立项、环评、登记注册、建设规划等方面实行一站式服务,创造良好的建设环境和生产经营环境。

  项目将分四期实施,其中一期、二期计划各投资40亿元,分别建设7.5GW,共计15GW高效太阳能电池项目,三期、四期计划各投资60亿元,分别建设7.5GW,共计15GW高效太阳能电池及配套项目。

  根据计划,一期7.5GW项目将于2020年3月前启动,在2021年内建成投产,后续项目将根据市场需求情况,在未来3-5年内逐步建成投产。

  若以目前市场主流电池价格测算,项目建成投产后预计将新增营业收入约300亿元/年,公司太阳能电池及配套项目产能将达60GW。与此同时,借助新项目的实施,以大尺寸规格、Perc+、Topcon及HJT等高效产品为主的技术选择将促进太阳能电池非硅成本持续下降。


来源:国际电力网



Legal statement:

1. The information reprinted or sorted out by the global website of Epec.com comes from official public channels or indicated sources. We are committed to providing reasonable, accurate and complete information, but do not guarantee the reasonableness, accuracy and completeness of the information. We are not responsible for any loss or damage caused by unreasonable, inaccurate or omitted information.

2. Epec.com fully respects the intellectual property rights of original authors. We solemnly remind visitors: when reprinting or using the information on this website, please obey relevant laws and regulations of the People's Republic of China. This website does not take any responsibility in case of related intellectual property disputes or other disputes. At the same time, this website has independent intellectual property rights for the original information and website logo. If the intellectual property rights of this website are infringed , this website has the right to pursue legal responsibility.

3. The information services published on this website are only for the purpose of information reference, learning or communication, and do not represent the views of this website, nor constitute any sales suggestions.

4. If this website inadvertently infringes the intellectual property rights of others, please write or call to inform, and this website will adjust or delete immediately.

If you have questions or need further assistance, please email: global.epec@sinopec.com.